KURRAM TANGI DAM MULTIPURPOSE PROJECT |
| LOCATION OF DAM | Khurram Tangi Dam Project in North Waziristan Agency (NWA) on Kurram River |
|
MAIN
COMPONENTS a. Dam Height Length Type b. RESERVOIR Gross storage Live storage c. IRRIGATION SYSTEM Length of Main canal F.S.Discharge Length of Distributaries Canal Command Area d. POWER HOUSE Installed capacity e. WEIR Length |
As per feasibility
Revised 295 Ft 322 Ft 931 Ft 1035 Ft Concrete faced Rock fill Dam (CFRD)
0.92 MAF 1.2 MAF |
| COMMENCEMENT | 48 months |
| COMPLETION | The construction work of the project is not started but started land acquisition |
| CONTACTOR | Contract not yet awarded |
| MANAGEMENT CONSULTANTS | Consultants not yet appointed |
| PROJECT COST PC-I | Rs.17205.268 |
|
PRESENT
STATUS a. Allocation current year b. Physical progress upto Dec.09 c. Expenditure ending June 09 d. Expenditure upto date February 2010 |
The project is re-activated and submitted the demand of fund for the current financial year 2009-2010 Due to non allocation of fund for the current financial year 2009-2010 Rs.56.297 M Rs.59.508 M |
|
PROJECT BENEFITS AND
ADVERSE IMPACT a. Environment b. Land submerges & Irrigated c. Population affection / improvement is standard d. Village / houses Dismantle/Reconstruction e. Economical Affects |
a. Flood Mitigation perennial water for irrigation improved environment of the area b. 10940 acres in tribal area and 1716 acres in FR Bannu/Distt Karak & Bannu c. 11687 population improve the standard of life of most backward area through construction of project d. 32 No villages and 1777 families will be affected which will be resulted. e. increase in agriculture production economic benefits from energy generation and flood mitigation |