| ALLAI KHWAR HYDROPOWER PROJECT | ||||
| Location |
The Project is located on Allai Khwar River, left bank tributary of Indus River near Besham District Battagram in N.W.F.P. at a distance of 245 Km from Islamabad. | |||
| Scope of Work |
Reservoir Dam structure Power intake Headrace Tunnel Surge Tank Pressure Shaft/Tunnel Power House (121 MW) Tailrace & Switchyard. | |||
| Objectives / Benefits | To provide cheaper power to the National Grid | |||
| Date of Commencement | Original (as per Contract) June 2003 | |||
| Date of Completion |
Original (as per Contract) |
Revised / Expected | ||
|
June 2007 |
Jan 2009 / Oct 2011 | |||
| Project Cost |
(Rs. Million) | |||
|
As per PC-I |
Local |
FEC |
Total | |
| 5124.284 | 3453.540 | 8577.824 | ||
| Salient Features | Design Discharge | 21 m3/s | ||
| Gross Head | 692 m | |||
| Headrace Tunnel | 2.366 km | |||
| Installed Capacity | 122 MW | |||
| Energy per annum | 463 GWh | |||
| Present Status / Progress |
Construction of weir structure sand trap pressure tunnel powerhouse tailrace & switchyard in progress. Designing manufacturing & installation of E&M equipment in progress. | |||
| Incharge of the Project |
Project Director Allai Khawar Hydropower Project WAPDA
Besham Contact No. 092-996-400269 | |||