ALLAI KHWAR HYDROPOWER PROJECT
Updated as on 14.10.2014
Location The project is located on Allai Khwar River, left bank tributary of Indus River near Besham District Battagram in Khyber Pakhtun Khwa province at a distance of 245 km from Islamabad.
Scope of Work Reservoir, weir structure, power intake, sand trap, pressure tunnel, power house (121 MW), tailrace and switchyard
Objectives / Benefits To provide cheaper power to the National Grid
Date of Commencement Original (as per Contract) June  2003
Date of Completion 

Original (as per Contract)

Revised / Expected

June 2007

Jan 2009 / Mar 2013
(MOU-2)

Project Cost
(as per Rev PC-I  Approved on 29.07.2011)

(Rs. Million)

Local

FEC

Total

7312.687 6522.261 13834.948
Salient Features Design Discharge 21 m3/s
Gross Head 692 m
Headrace Tunnel Length 2.366 km
Installed Capacity 121 MW
Energy per annum 463 GWh
Present Status / Progress

- The power house is in commercial operation since 25th March 2013.

       - The power house has supplied 825.739 M kWh to the national grid upto 30.09.2014.

Incharge of the Project Name: Engr. Haji Muhammad
Designation: Resident Engineer (O&M)
Address: Allai Khwar Hydel Power Station
WAPDA, Besham
Contact No. 092-996-400106