PAKISTAN
WATER AND POWER DEVELOPMENT AUTHORITY
BRIEF
ON
CHASHMA RIGHT BANK
IRRIGATION PROJECT

YEAR
-2010
CHASHMA RIGHT BANK IRRIGATION PROJECT D.I.KHAN
CHASHMA RIGHT BANK CANAL
Chashma Right Bank canal off-takes from Chashma Barrage on its right
bank and extends south ward upto Tounsa Barrage on Indus River.
SALIENT
FEATURE
| 1.
Cultivable Command Area |
606,000 Acres
/245,240 Hectares |
|
K.P.K |
366,000 Acres /148,115 Hectares |
|
Punjab |
240000 Acres /97,125 Hectares |
|
2. i. Length of Canal |
170 Miles/274 KMs |
|
K.P.K |
106 Miles/171 KMs |
|
Punjab |
64
Miles/103 KMs |
|
ii. Distributaries |
|
|
Nos/Length |
72
Nos 666 Miles/ 1065 KMs |
|
K.P.K |
42
Nos 391 Miles /625 KMs |
|
Punjab |
30
Nos 275 Miles /440 KMs |
|
Stage-I |
13
Nos 141 Miles/227 KMs |
|
Stage-II |
15
Nos 105 Miles/168 KMs |
|
Stage-III(K.P.K) |
14
Nos 145 Miles/230 KMs |
|
Punjab |
30
Nos 275 Miles /440 KMs |
| |
No |
Length in (Ft.) |
Disch: in (Cusecs) |
|
iii. Flood Carrier Channel |
|
Stage-I
Stage-II
Stage-III |
18
22
27 |
264,000
727,0516
898,834 |
149,160
140,800
459,000 |
|
Total |
67
|
1,888,885 |
748,960 |
| |
475.70 KMs. 21,208 Cumecs |
| 3.
Discharge Capacity |
4879 Cusecs/ 138.16 Cumecs |
|
K.P.K |
3045 Cusecs/86.23 Cumecs |
|
Punjab |
1,834 Cusecs/ 51.93 Cumecs |
| 4.
Financial Status |
|
Approved PC-I (4th Revision) |
Rs.
17,096.865 Million |
|
Stage-I |
Rs.
2,491 Million |
|
Stage-II |
Rs.
2,334 Million |
|
Stage-III |
Rs.
12,272 Million |
|
Expenditure Incurred (Upto June-2005) |
Rs.
17004.197 Million |
| 5.
Date of completion |
December, 2003 |
| 6.
Water Allowance |
7.62 Cs / 1000 Acres |
| 7.
Cropping Intensity prior to inception of the Project |
28% |
| 8.
Ultimate Cropping Intensity on full development of the Project
|
142% |
| |
|
|
Project Concept
|
|
Stage_I |
|
Length
Commenced
Completed
CCA
Water Allocation
Distributaries
Cost |
52
miles
1978
1986
150,000 Acres
1226 Cusecs
13 Nos
Rs. 2491 million (as per 4th Revised PC-I). |
|
Stage_II |
|
Length
Commenced
Completed
CCA
Water Allocation
Distributaries
Cost |
24
miles
1988
1994
94,000 Acres
800 Cusecs
15 Nos
Rs. 2,334 million (as per 4th Revised PC-I). |
|
Stage_III |
|
Length
Commenced
Completed
CCA
Water Allocation
Distributaries
Cost |
94
miles (K.P.K 30 Miles & Punjab = 64 Miles
1995
2003
362,000 Acres K.P.K = 126,000 & Punjab=236,000
2853 Cusecs K.P.K = 1053 & Punjab = 1800
44 Nos K.P.K=14 Nos & Punjab = 30 Nos
Rs. 12,272 Million |
|
Donors |
ADB |
KfW |
GOP |
|
Stage_I |
79% |
- |
21% |
|
Stage_II |
79% |
- |
21% |
|
Stage_III |
65% |
14% |
21% |
ADDITIONAL CIVIL WORKS
Chashma
Right Bank Irrigation Canal was constructed to cultivate an area of
606000.00 Acres out of which, 366000.00 Acres in NWFP and 240000 Acres
in Punjab. The Project has been completed since December 2003.
The 4th
Revised PC-I to the tune of Rs. 17,097.000 million was expired in June
2005, but some essential Additional Civil Works recommended by GRSC/ ADB
and clearance of outstanding Liabilities of various contracts at the
Project were found necessary.
The
Additional Civil Works recommended by GRSC/ADB and clearing the
Outstanding Liabilities or various contracts could not carried out
during the implementation of 4th Revised PC-I for CRBC Project WAPDA D.I.
Khan.
A meeting
with mid term Review Mission (ADB) was held in Planning Commission, It
was decided that 4th Revised PC-I pertaining in CRBC under Loan No. 1146
Pak(SF) should be closed and a new PC-I for execution of GRSC
recommended works and clearing the Outstanding Liabilities of completed
contracts to be prepared by WAPDA.
In view of
foregoing a new PC-I was prepared and have been approved by ECNEC to the
const of Rs. 865.834 million with a foreign component of Rs. 684.409
million.
The works
are scattered in different places and were bifurcated in small
contracts. Almost all the contracts have been completed.
Revised
PC-I amounting to Rs. 1150.000 million was submitted to the P&D
Division Islamabad and the same has been recommended by CDWP for
approval of ECNEC vide letter No. 10(648)OIA-II/PC/2010 Islamabad, the
15th November, 2011.
The
physical & Financial Progress of Additional Civil works & Outstanding
Liabilities upto 31.03.2012 are as under.
| i. |
Physical Progress (Based on Revised PC-I) |
91% |
| ii. |
Financial Progress Against Civil Works (Based on Revised PC-I) |
88% |
Updated As on
31.03.2012.
|
 |
 |
|
V.R BRIDGE ON TOA
FCC AT RD: 50+400 |
APPROACH ROAD TO
V.R BRIDGE ON TOA FCC AT RD:50+400 |
|
 |
 |
|
BOX CULVERT AT
DIKHAN – TANK ROAD |
BOX CULVERT AT
DIKHAN – TANK ROAD |
|
 |
 |
|
V. R BRIDGE ON CRB
MAIN CANAL AT RD: 672± |
V.R
BRIDGE ON CRB MAIN CANAL AT RD:169± |
|
 |
 |
|
V.R
BRIDGE ON CRB MAIN CANAL AT RD:169± |
V. R BRIDGE ON CRB
MAIN CANAL AT RD: 672± |
|