New Connection Procedures

  1. The prospective consumer can get free of cost an application form from the Sub Division of concerned Distribution Electric Supply Company situated in his area.

  2. The application form duly filled in has to be submitted in the above Sub Division, where the concerned Clerk will issue receipt as an acknowledgement having received the application form.

  3. The new connection application will be processed in the Sub Division and the connection would be installed in 35 to 45 days. In case any connection is not feasible due to any technical or any other reason, the prospective consumer would be informed accordingly with reason for rejection of application.

  4. Documents recquired for new connection.

    • Copy of ID card.

    • Neighbour bill.

    • Filled application form.



Get New Application Form

The prospective consumer can also get free of cost an application form from the Sub Division of Distribution Electric Supply Company situated in his area. The specimen of the simplified new application form is attached. The same can be downloaded from this page.


You can also download the form by clicking the following link.

Download Application Form
You will require Acrobat Reader to read this form.

[the authority
[power wing
[water wing
[information technology
[ongoing projects
[investors information
[future projects
[customer services
[training
[news & media
[home [back