REHABILITATION OF JABBAN HYDROELECTRIC POWER STATION |
|||
| Location |
Jabban Hydroelectric Power Station project site is located in District Malakand (PATA) Khyber Pakhtunkhwa at a distance of 210 km from Islamabad, 45 km from the city of Mardan and 7 km upstream of 20 MW Dargai Hydroelectric Power Station. |
||
| Description |
Irrigation System:
Old Jabban Power
Station:
Fire Incident:
Project Objectives: |
||
|
Salient Technical Features (After Rehabilitation) |
|||
| Installed Capacity | 22 MW (4 Units of 5.5 MW each) | ||
| Annual Net Electrical Output | 122 GWh | ||
| Design Discharge | 34 m3 /sec (8.5 m3 / sec per unit) | ||
| Rated Net Head | 76.8 m | ||
| Generation Voltage | 11 KV | ||
| Transmission Voltage | 132 KV | ||
| Salient Financial Features | |||
| Project Cost as per revised PC-I | Total Rs. 3753.575 million Foreign Rs. 1649.485 million Local Rs. 2104.090 million |
||
| Generation cost per unit | Rs. 3.25 | ||
| Cost per KW of installed capacity | Rs. 169, 745 (US$ 1997 / KW) | ||
| Benefit Cost Ratio | 1: 2.14 | ||
| Project Features | |||
| Consultant | M/s NESPAK | ||
| Contractor | HRL-CCPG JV (Habib Rafique Ltd. (Pakistan) & Central China Power Group China). | ||
| Sub Contractor | |||
| - Powerhouse | M/s Zhejiang Jinlun Electro-mechanic Co. Ltd. Chine. | ||
| - Sub Station | M/s Areva T&D Pakistan (Pvt. ) Ltd. | ||
| Financing AFD (France) | Euro 25.0 Million | ||
| Contract Cost (Million) | F.CC (US$) | L.CC (Pak Rs) | Date |
| Original Cost: | 17.905 | 682.127 | |
|
Variation order No. 1 new penstock 3&4 |
-- |
105.844 | March 12,2010 |
|
Variation order No. 2 deletion of workshop |
-- |
(-) 1.204 | June 15,2010 |
| Revised Contract Price | 17.905 | 786.767 | |
| Contract Price in Pak Rs: | 2326.597 | M (1 US$ = 86 Rs.) | |
| Date of Commencement | 19-02-2010 | ||
| Completion period | 21 months from Order to Commence. | ||
| Commercial Operation Date (Final) As per Contractual Plan As Expected Financial Progress (upto June 2012): |
18-11-2011 31-12-2012 25.89% |
||
| General |
i) Visit of General
Manager (Hydel-Dev:) & RSWI's Inspection team to Jabban HEPS
Project on 12-06-2012.
General Manager (Hydel-Dev:)
alongwith RSWI's Inspection team arrived at Jabban HEPS Project site on
16-06-2012 at 10.00 AM. Chief Engineer/PD Jabban HEPS Project & Chief
Engineer Warsak welcomed them at Jabban. They visited the site and
discussion held about slow pace of work at site. Chief Resident Engineer
NESPAK Jabban and Project Manager HRL-CCPG JV were also present at site.
C.R.E. NESPAK expressed his views that contractor delayed the submittals
and has not submitted drawings for ear thing mesh of Power House in time
that is why works is held up at site. Project Manager HRL-CCPG JV
restrained that consultants are rigid and take too much time in
reviewing the drawings. Even if the drawings approved and the comments
on the drawings are not proper. Representative of RSWI's team also
viewed the comments on approved drawing and said that comments are ok. ii) Visit of General Manager (Hydel-Dev:) & AFD's Inspection team on 30-06-2012. General Manager (Hydel-Dev:) CE Warsak & SE/PD Jabban warmly welcomed the AFD's Inspection Team. General Manager (Hydel-Dev:) briefed the team about the ongoing activity in Jabban HEPS Project and appraised the team updated about the status of Jabban HEPS Project. During discussion about the slow progress, HRL pointed out about the slow release of fund from AFD. However, AFD's team clarified that the manufacturing of the E&M equipment may be expedited and FAT certificate of the already manufactured E&M equipment may be submitted with the relevant draw down request. AFD's Inspection Team insisted on FAT certificates for release of fund to WAPDA. G.M (Hydel-Dev:) told that a team of Engineers four i.e two from WAPDA & two from NESPAK have already been gone to China and soon will returned to Pakistan. When they arrived the status of FAT certificates of the E&M equipment will be confirmed and conveyed. AFS's Inspection Team then visited the site and expressed their views about the slow pace of work at site. After visiting the site they were taken to Dargai rest house for lunch. They departed from Dargai rest house at 03.00 P.M.
|
||
| Work Progress (June-2012): |
1) Power House Area: Unit No. 4.
Unit No. 3&2
Unit No. 1 a) 1st lift
concrete of 61 Cum poured at Penstock entrance area concrete on
01-06-2012.
2) Penstock Area. 3) Forebay. 4) 132 KV
Switchyard. Dispersal of
Power from Power House: |
||
| Updated as on 25.07.2012 | |||
|
|
|||
|
|
|||
|
|
|||
|
|
|||
|
|
|||