Hydel GenerationSalient FeaturesPower StationsPerformanceMangla Dam
Tarbela DamWarsak Dam
Chashma Hydropower Project

Warsak Dam


Warsak Hydro Electric Power Project is located on River Kabul at about 30 km from Peshawar in North-West Frontier Province of Pakistan. The project financed by Canadian Government was completed under COLOMBO PLAN in two phases.

The Project Main Features The project consists of a mass concrete gravity dam with integral spillway, power tunnel, power station, a concrete lined 10 feet diameter irrigation tunnel on right bank and a 3 feet diameter steel pipe irrigation conduit on the left bank of the reservoir. The 250 ft. high and 460 ft. long dam with reservoir of 4 square miles had a live storage capacity of 25,300 acre-feet of water for irrigation of 119,000 acres of land and meeting power generation requirement. A spillway with nine gates is capable to discharge 540,000 cusecs of flood water.

POWER STATION
The first phase including construction of Dam, Irrigation tunnel, civil works for Phase-II and installation of four units each of 40 MW capacity with 132 kv transmission system, was completed in 1960 at a total cost of Rs.394.98 million. Two additional generating units each of 41.48 MW capacity were added in 1980-81 at a cost of Rs.106.25 million as second phase of the project.

Warsak Dam has now completely silted up and practically there is no available storage. Power generation is being achieved according to water inflows in River Kabul like a "Run-of-the-River' project. Lean flow period at Warsak is observed from October to March during which capability reduces to about 100 MW (Peak).

Salient features / Principal data of main components of Warsak Dam and Power House.

Warsak Dam
Type Mass Concrete Gravity Dam

Height
250 ft. 76.20 meters

Length
460 ft. 140.21 meters

Reservoir
Max. Conservation Level 1270 ft. SPD 387.10 meter
Design Live Storage 25300 AF
Existing Live Storage Nil
Surface Area 4.0 sq. miles 10.36 sq. km

Main Spillway
Type Overflow
Capacity Per Gate 60,000 cusecs
No. of Gates 9 (Nine)
Size of Gate 40 ft. wide
40 ft. high
12.19x12.19 meters

Power House
UNITS 1~4 5~6
Turbine (Francis-Vertical)
Output (BHP)

Rated Head (Ft. of Water)

Make

55000

144

Dominion Engg. Co.
Canada

57000

144

Dominion Engg. Co.
Canada

Generators (Umbrella Type)
Output (MVA)

Output (MW)

Output (P.F)

Output (K.V)

Rated Speed (RPM)

Make

40

40

1.0

11.0

136.3

Canadian General Elec. Co. Ltd.

48.8

41.5

0.85

11.0

136.3

Canadian General Elec. Co. Ltd.

Transformers
Capability (MVA)

Voltage Ratio (KV)

Make

13.33 Per Phase
(Single-Phase Bank)

11/132 KV

Sarranti, Canada

48.8
(Three-Phase)

11/132 KV

Westinghouse

Project Benefits
Besides providing irrigation water from the dam during early years of its life, the project has generated over 36.261 Billion KWh of cheap energy since its commissioning. Annual generation during 2008~2009 was 994.404 Million KWh while the station shared 214 MW peak load.


Updated:  September  30, 2009
 
[the authority
[power wing [power generation [power transmission [power distribution
[water wing
[ongoing / future projects
[customer services
[training
[investors information
[news & media
[home [back