Golen Gol Hydropower Project

Location: District Chitral, Khyber Pukhtunkhwa
 Salient Features
Weir Height 12.00m
Length Of Tunnel 3.8 Km
Gross Head 436 m
Desighn Discharge 30 m3/Sec
Installed Capacity 108 MW
Objectives To Generate Electricity
Execution By WAPDA
Dam Type Weir / Run of River Project
Execution By WAPDA
Supervision Consultants Joint Venture of M/s. Fichtner Germany, M/s. PES Pakistan, M/s BAK Pakistan & M/s DMC Pakistan
Contractors
LOT-2(Civil work) M/S SAMBU SARCO (JV)
LOT-3.1 (Civil Works of PowerHouse) M/S SAMBU SARCO (JV)
LOT-3.2 (E&M Works) M/S Andritz
LOT-4 Package-1 & 2 (T/Line) M/S NETRACON
Donor Agency
Saudi Fund (Lot-2) Us $40+57.800=97.8 Million
Kuwait Fund for Lot 3.1 &3.2 US $ 37 Million

OFID Fund (Lot-4 Pak-1&2) US $ 30 Million

USAID (Lot3.2) US$ 35.619 Million

Commencement Date July 2002 / 01.02.2011
Completion Date June 2006 / Expected May, 2018
Financial Status Local (Rs. Million) FEC (Rs. Million) Total (Rs. Million)
Approved PC-I Cost 02.09.2002   4397.008 2638.120 7035.128
PSDP Allocation 2017-18 3848 2407 6255
Original PC-I Cost Rs. 7035.128 Million
Revised PC-I Cost Rs. 29077.701 Million Approved on30.09.2016

 

Status                               

Overall physical progress achieved up to October 2017 is 85.76%

 

Incharge of the Project

 Engr. Muhammad Javed Afridi Chief Engineer/PD