Bara Dam Project

Bara Dam Project

Location
On Bara River at the confluence of Mastura River in Khyber Agency, FATA.
Salient Features
Dam Type Earth Core Rockfill Dam
Height of Dam 302 ft
Gross Storage Capacity 85,363 AFT
Live Storage Capacity 62,434 AFT
CCA 41,729 Acres
Power Generation 5.8 MW (38.1 GWh)
Execution by WAPDA
Contractor -
Donor Agency Govt. Of Pakistan
Consultants M/s NESPAK
Commencement Date -
Completion Date Construction Period 5 years
Financial Status Local (Rs. Million) FEC (Rs. Million) Total  (Rs. Million)
Approved PC-I Cost 14,208.00 - 14208.00
PSDP Allocation 2018-2019 - - -

Status:       

 • Feasibility Study completed in 2008 by NESPAK under FATA Development Authority. FATA Development Authority in Sept. 2008 requested WAPDA to take-up the project for implementation.
• PC-II Proforma for Detailed Engineering Design, Tender documents & PC-I has been submitted to MoWR on 09.10.2018, which is under process of approval.

Incharge of the Project:  

Shahid Mahmood
General Manager (Hydro) Planning,
WAPDA, Sunny View, Lahore
Contact No. 0092-42-99202717
Cell No. 0333-4654348

Read 21800 times