English Chinese (Simplified) Urdu 

Warning: file_get_contents(http://graph.facebook.com/?ids=http://www.wapda.gov.pk/index.php/projects/water-sector/under-construction/rbod-i): failed to open stream: HTTP request failed! HTTP/1.1 403 Forbidden in /home/wnppitc/public_html/plugins/content/bt_socialshare/bt_socialshare.php on line 895

Warning: file_get_contents(http://graph.facebook.com/?ids=http://www.wapda.gov.pk/index.php/projects/water-sector/under-construction/nai-gaj-dam): failed to open stream: HTTP request failed! HTTP/1.1 403 Forbidden in /home/wnppitc/public_html/plugins/content/bt_socialshare/bt_socialshare.php on line 895

Warning: file_get_contents(http://graph.facebook.com/?ids=http://www.wapda.gov.pk/index.php/projects/water-sector/under-construction/rbod-iii): failed to open stream: HTTP request failed! HTTP/1.1 403 Forbidden in /home/wnppitc/public_html/plugins/content/bt_socialshare/bt_socialshare.php on line 895

Warning: file_get_contents(http://graph.facebook.com/?ids=http://www.wapda.gov.pk/index.php/projects/water-sector/under-construction/muzaffargarh-t-p-link-canal-lining): failed to open stream: HTTP request failed! HTTP/1.1 403 Forbidden in /home/wnppitc/public_html/plugins/content/bt_socialshare/bt_socialshare.php on line 895
Under Construction

Under Construction (4)

 (RIGHT BANK OUTFALL DRAIN PROJECT(RBOD-I))

Location: Project area lies within Larkana, Kamber-Shahdadkot, Dadu & Jamshoro districts of Sindh.
 

Scope of work: 

       The works includes:
  1. Indus Link Widening and Construction.
    • Balance Work of IL-1 including its widening from RD 0 to 22+017 - Contract No. RI(E).
    • Widening of IL-2 & IL-3 from RD 22+017 to 80+282 - Contract RI(B).
  2. Extension of RBOD Up to Miro Khan Zero Point.
    • Extension to MKZP from RD 0+000 to 132+600 – Contract RI(A).
  3. Remodeling of MNVD for 3500 Cusecs drainage effluent.
    • Remodeling of MNVD from RD 220+000 to 342+220 – Contract No. RIII(a/1).
    • Remodeling of MNVD from RD 110+000 to 220+000 – Contract No. RIII(a/2).
    • Remodeling of MNVD from RD 000+000 to 110+000 – Contract RIII(a/3).
  4. Rehabilitation of Rato Dero Surface Drainage Project.
    • Balance work of Rato Dero Pump Station – Contract RTD-1(B).
  5. Rehabilitation of Miro Khan Surface Drainage System. (Work to be executed by Irrigation Department (GoS)).
  6. Rehabilitation of Shahdadkot Surface Drainage System. (Work to be executed by Irrigation Department (GoS)).
  7. Monitoring the Quality of Effluent of Project area work is being carried out through SWHP as deposit work.
  8. New Hamal Regulator at RD 342 of MNVD – Contract No. RIII(a/4).
  9. Construction of New 62 additional structures. Work yet to be started.

Objectives / Benefits:

  • The primary objectives of the works included in LIRB Project Stage-I Priority Works is to provide much needed outfall facilities for the existing and proposed drainage projects, rehabilitation of existing drainage projects on Indus Right Bank in Northern Sindh.
  • The priority works would increase crop production through increase in cropping intensity and yields and also decrease agricultural risks on 842,500 acres commanded by the Rice Canal, North West Canal and Dadu Canal.
  • Utilization of non-saline effluents to recharge lakes or feed irrigation system and segregate saline effluent for diversion into sea through RBOD-II.
  • Facilitate absorption of hill torrents.
Commencement Date July,1994
Completion Date

30-06-1998 (As per Original approved PC-i).      

31-12-2008 (As per 1st revised approved PC-I).

30-11-2019 (As per 2nd revised approved PC-I).

Financial Status Local (Rs. Million) FEC (Rs. Million) Total (Rs. Million)
PC-1 (Original) Rs.4395.00 - Rs.4395.00
PC-1 (Revised) Rs.14707.143 - Rs.14707.143
(Approved by ECNEC on 30-11-2006).
2nd revised PC-I Rs.17505.018 - Rs.17505.018
ECNEC has approved on 26.07.2017 (minutes are yet to be issued & circulated)

Salient Features

a). Gross Command Area:  :       517,310 Acres.

b). Components:

1) Indus Link Widening and Construction.
Balance work of IL-1 including its widening from RD 0+000 to 22+017 Contract No. R1(E) Length : 17.87 KM
Capacity: 3500 Cusec
Contract Cost: Rs.152 Million
Progress: 81.91%
& Contract terminated
Widening of IL-2 & IL-3 for 3500 Cusec from RD 22+017 to 80+282 Contract No. R1(B). Length : 6.71 KM
Capacity: 3500 Cusec
Contract Cost: Rs.72.59 Million
Progress: 87.03%
& Contract terminated
2) Extension of RBOD Up to Miro Khan Zero Point.
Extension to MKZP from RD 0+000 to 132+600 Length : 40.41 KM
Capacity: 2322 Cusec
Contract Cost: Rs.609.547 Million
Revised: (592.157) Million
Progress: 85.60%
& Contract terminated
3) Remodeling of MNVD for 3500 Cusecs drainage effluent.
Remodeling of MNVD from RD 220+000 to 342+220. Contract No. R-III(a/1). Length : 37.25 KM
Capacity: 3500 Cusec
Contract Cost: Rs.525 Million
Progress: 100%
& Work completed
Remodeling of MNVD from RD110+000 to 220+000. Contract No. R-III(a/2). Length : 33.52 KM
Capacity: 3500 Cusec
Contract Cost: Rs.315 Million
Progress: 100%
& Work completed
Remodeling of MNVD from RD 000+000 to 110+000. Contract No. R-III(a/3). Length : 33.52 KM
Capacity: 3500 Cusec
Contract Cost: Rs.367.569 Million
Progress: 63%
& Contract terminated
4) Rehabilitation of Rato Dero Surface Drainage Project.
Balance work of Rato Dero Pump Station - Contract No. RTD-(B).

Contract Cost : Rs. 16.500

Progress : 100%

Work has been completed and handed over to Provincial Irrigation Department GoS on 15.02.2016.

5) Rehabilitation of Miro Khan Surface Drainage System.

Earthwork: 80.697 Mcft

Structure: 15 Nos.

Contract Cost :270.640 Million

Progress : Work to be executed by Irrigation Department (GoS).

6) Rehabilitation of Shahdadkot Surface Drainage System. 

Earthwork: 60.210 Mcft

Structure: 178 Nos.

Contract Cost : 298.496 Million

Progress : Work to be executed by Irrigation Department (GoS).

7) Monitoring the Quality of Effluent of Project area work is being carried out through SWHP as deposit work.

Work is being carried out by SWHP through Deposit work

8) New Hamal Regulator at RD 342 of MNVD – Contract No. RIII(a/4).

Contract Cost :Rs. 175.896

Progress : 100%

Work has been completed and handed over to Provincial Irrigation Department GoS on 16.07.2015.

9) Construction of New 62 additional structures.

Work yet to be started

Present Status / Progress
1). Indus Link Widening and Construction.
  Balance work of IL-1 including its widening from RD 0+000 to 22+017 Contract No. R1(E) The Authority accorded approval for release to the Contractor M/s Abrar Malik & Company from further performance. Upto date progress 81.91%.
  Widening of IL-2 & IL-3 for 3500 Cusec from RD 22+017 to 80+282 Contract No. R1(B). The Authority accorded approval for release to the Contractor M/s Malik Riaz & Co. from further performance. Upto date progress 87.03%.
2). Extension of RBOD Up to Miro Khan Zero Point.
  Extension to MKZP from RD 0+000 to 132+600 Contract No. RI(A). The Authority accorded approval for release for Contractor M/s Khyber Grace (Pvt.) Limited from further performance. Upto date progress 85.60%.
3). Remodeling of MNVD for 3500 Cusecs drainage effluent.
  Remodeling of MNVD from RD 220+000 to 342+220. Contract No. R-III(a/1). Work completed by the Contractor 100% Taking Over Certificate and Defects Liability Certificate (DLC) issued to the Contractor.
  Remodeling of MNVD from RD110+000 to 220+000. Contract No. R-III(a/2). Work completed by the Contractor 100% Taking over Certificate and Defect Liability Certificate (DLC) approved by the Authority and issued to the Contractor.
  Remodeling of MNVD from RD 000+000 to 110+000. Contract No. R-III(a/3). The Authority accorded approval for release for Contractor M/s Muhammad Ayub & Brothers (Pvt.) Limited from further performance of Contract. Upto date progress 63%.
4). Rehabilitation of Rato Dero Surface Drainage Project.
  Balance work of Rato Dero Pump Station Contract No. RTD-(B). Work has been completed and handed over to Provincial Irrigation Department Government of Sindh on 15.02.2016.
5). Rehabilitation of Miro Khan Surface Drainage System. Work to be executed by Irrigation Department Government of Sindh.
6). Rehabilitation of Shahdadkot Surface Drainage System. Work to be executed by Irrigation Department Government of Sindh.
7). Monitoring the Quality of Effluent of Project area work is being carried out through SWHP as deposit work. Work is being carried out by Surface Water Hydrology Project (SWHP) through Deposit work.
8). New Hamal Regulator at RD 342 of MNVD – Contract No. RIII(a/4). Work has been completed and handed over to Provincial Irrigation Department Government of Sindh on 16.07.2015.
9). Construction of New 62 additional structures. Work yet to be started

 Incharge of the Project:

Muhammad Ahtesham-ul-Haq,

Project Director,

RBOD-I Project WAPDA,

Sukkur.

(Right Bank Outfall Drain Project (RBOD-I))

 

Location: The Nai Gaj Dam Project is being constructed across Nai Gaj River, at latitude 26° 52'N and longitude 67° 19'E and is located 65 Km North-West of Dadu City in Sind Province.
Salient Features
 Dam Type Central Core Earth Fill Dam
 Height of Dam 194 ft
 Gross Storage Capacity 300,000 AF
 Live Storage Capacity 160,000 AF
 CCA 28,800 Acres
 Power Generation 4.2 MW
Execution by WAPDA
Supervision Consultants M/s Techno Consult International. (Pvt.) Ltd in association with Hydro Power Engineering
Contractor M/s NEIE-SMADB-LILLEY-RMS(JV)
Donor Agency Govt. of Pakistan
Commencement Date April 25, 2012
Completion Date

April 24, 2015 (Original)

June 30, 2019 (Expected)

Financial Status Local (Rs. Million) FEC (Rs.Million) Total (Rs. Million)
Original PC-I Cost 16,510.02  414.49 16,924.61
1st Revised PC-I Cost 26,236.03   26,236.03
PSDP Allocation FY 2016-17 1,500.00   1,500.000

 

Status:-

  Over all Physical Progress is 48.40%.        

Incharge of the Project: 

     Engr. Muhammad Farhat Kamal

     Chief Engineer/Project Director
     Nai Gaj Dam Project
     0314-2860008

 Location: Project is located on the right bank of River Indus lies between the latitude of 27o-54o & 28o-40o’ and longitude of 67o-39o and 68o-51o . Mostly it is spread within the area of Districts Nasirabad and Jafarabad of Balochistan and District Jacobabad and Kambar Shahdadkot  of Sindh Province.
Scope of work: To provide the direly needed effluent disposal facilities for existing and proposed drainage projects to reclaim the agricultural land converted into ponds of water and Irrigation surplus. Conservation of Hamal and Mancher Lakes and environment condition will improve over gross commanded area (GCA) of 287,106 hectares. The Project is comprising of following components:
  • Hairdin Carrier Drain Extension from Chukhi to MKZP and 6km North of Chukhi.
  • Construction of Irrigation channel for reutilization of 400 cusec of Balochistan effluent.
  • RBOD Extension from MKZP to Hairdin Pump Station.
  • Re-modelling of Shahdad Kot Main Drain.
  • Surface Drainage System of Usta Muhammad Unit.
  • Hadero Drainage Unit.                                    
  • Usta Muhammad Drainage Unit.    
Salient Features
EIRR 14.80%
Executing Agency WAPDA
Consultants M/S NDC, BARQAAB, EASE-PAK(JV) & Consultancy services expired on 30.12.2010
Contractor

M/s Khyber Grace (Pvt) Ltd. Islamabad

M/s Ayub & Brothers (Pvt) Ltd. Islamabad

M/s Tameer Associates, Lahore

Commencement Date July 2004
Completion Date 30.11.2019 (Revised)
Financial Status 

Local

(Rs. Million)

FEC

(Rs. Million)

Total

(Rs. Million)

Approved PC-I Cost 4,485.200 - 4485.200
1st Revised Updated PC-I Cost 10,804.540  (ECNEC approved in its meeting held on 26.07.2017)

PSDP Allocation

2017-2018

1200.000 - 1200.000

 

Status:

i. Construction of Hairdin Carrier drain Extension from Chukhi to MKZP and 6Km North of Chukhi Contract R-III (c) completed.

Earth Work   141.360 Mcft.

Structure      36 Nos.

ii. Construction of RBOD Extension from MKZP to Hairdin Pump Station Contract R-III (b) was terminated by the Authority due to financial constraints.

Earth Work   222.920 Mcft.

Structure      85 Nos.

iii. Construction of Irrigation Channel up to Chitti River River Contract R-III (f) substantially completed.

Earth Work   46.991 Mcft.

Structure      79 Nos.

iv. Construction of Hadero Drainage Unit Contract R-III (d/1) was terminated by the Authority due to financial constraints.

Earth Work   39.534 Mcft.

Structure      54 Nos.

v. Construction of Usta Muhammad Drainage Unit Contract R-III (d/2) was terminated by the Authority due to financial constraints.

Earth Work    43.050 Mcft.

Structure       77 Nos.

vi. Re-modeling of Shahdad Kot Main Drain contract No. R-III (b/1) completed.

Earth Work    132.019 Mcft.

Structure       31 Nos in Progress.

vii. Arrangements for opening of Syphon No. 2 at Saifullah Magsi Canal Contract No. R-III (b/2) is substantially completed.

Earth Work     6.746 Mcft.

Structure        02 Nos.

Incharge of the project      

  Engr. Fareed Ahmed Mughal

  Project Director

REMEDIAL MEASURES  TO  CONTROL WATER  LOGGING  DUE TO MUZAFFARGARH & T.P LINK CANALS

Location

Tehsil Kot Addu, District Muzaffargarh, Punjab

Scope of Work
  • Lining of Muzaffargarh Canal along with drainage system under lining from RD 0+000 to 206+700 (63 Km).
  • Rehabilitation of Existing Structure.
  • Construction of new drainage & rehabilitation of existing drains along T.P.Link.        
Project Benefits
  • 35% of total command area of Muzaffargarh Canal will be rehabilitated and 0.3 million acres lands of Kot Adu will be bring back for cultivation.
  • Increase in per capita income of inhabitants.
  • Living standard of Inhabitants will enhance.
  • Reduction in migration, due to waterlogging.
  • Health of effectees will improve.
  • Education & social activities will enhance.
  • Increase value of land & ensure economic prosperity.
  • Revenue of Government will increase, due to establishment of agro based industry.
  • Water pollution, due to stagnant water will be eliminated.
  • Good quantity water will be available for human being as well as livestock.
  • Annual benefits Rs. 1.68 Billion per annum.    
Salient Features  
Length of Canal Lining 63 km
Commencement Date January 07, 2014
Completion Date January 06, 2016
Financial Status Local (Rs. Million) FEC (Rs. Million) Total (Rs. Million)
PC-I Cost Approved on 13.09.2013 8,565.000 - 8,565.000
PSDP Allocation for 2015-2016 800.000 - 800.000
Up to date Expenditure 1,367.984 - 1,367.984

Status

  • Physical Progress             11%