RBOD-III

 Location: Project is located on the right bank of River Indus lies between the latitude of 27o-54o & 28o-40o’ and longitude of 67o-39o and 68o-51o . Mostly it is spread within the area of Districts Nasirabad and Jafarabad of Balochistan and District Jacobabad and Kambar Shahdadkot  of Sindh Province.
Scope of work: To provide the direly needed effluent disposal facilities for existing and proposed drainage projects to reclaim the agricultural land converted into ponds of water and Irrigation surplus. Conservation of Hamal and Mancher Lakes and environment condition will improve over gross commanded area (GCA) of 287,106 hectares. The Project is comprising of following components:
  • Hairdin Carrier Drain Extension from Chukhi to MKZP and 6km North of Chukhi.
  • Construction of Irrigation channel for reutilization of 400 cusec of Balochistan effluent.
  • RBOD Extension from MKZP to Hairdin Pump Station.
  • Re-modelling of Shahdad Kot Main Drain.
  • Surface Drainage System of Usta Muhammad Unit.
  • Hadero Drainage Unit.                                    
  • Usta Muhammad Drainage Unit.    
Salient Features
EIRR 14.80%
Executing Agency WAPDA
Consultants M/S NDC, BARQAAB, EASE-PAK(JV) & Consultancy services expired on 30.12.2010
Contractor

M/s Khyber Grace (Pvt) Ltd. Islamabad

M/s Ayub & Brothers (Pvt) Ltd. Islamabad

M/s Tameer Associates, Lahore

Commencement Date July 2004
Completion Date 30.11.2019 (Revised)
Financial Status 

Local

(Rs. Million)

FEC

(Rs. Million)

Total

(Rs. Million)

Approved PC-I Cost 4,485.200 - 4485.200
1st Revised Updated PC-I Cost 10,804.540  (CDWP recommended for its approval from ECNEC on dt: 29.11.2016)

PSDP Allocation

2016-2017

1,300.000 - 1,300.000

 

Status:

i. Construction of Hairdin Carrier drain Extension from Chukhi to MKZP and 6Km North of Chukhi Contract R-III (c) completed.

Earth Work   141.360 Mcft.

Structure      36 Nos.

ii. Construction of RBOD Extension from MKZP to Hairdin Pump Station Contract R-III (b) was terminated by the Authority due to financial constraints.

Earth Work   222.920 Mcft.

Structure      85 Nos.

iii. Construction of Irrigation Channel up to Chitti River River Contract R-III (f) substantially completed.

Earth Work   46.991 Mcft.

Structure      79 Nos.

iv. Construction of Hadero Drainage Unit Contract R-III (d/1) was terminated by the Authority due to financial constraints.

Earth Work   39.534 Mcft.

Structure      54 Nos.

v. Construction of Usta Muhammad Drainage Unit Contract R-III (d/2) was terminated by the Authority due to financial constraints.

Earth Work    43.050 Mcft.

Structure       77 Nos.

vi. Re-modeling of Shahdad Kot Main Drain contract No. R-III (b/1) completed.

Earth Work    132.019 Mcft.

Structure       31 Nos in Progress.

vii. Arrangements for opening of Syphon No. 2 at Saifullah Magsi Canal Contract No. R-III (b/2) is substantially completed.

Earth Work     6.746 Mcft.

Structure        02 Nos.

Incharge of the project      

  Engr. Fareed Ahmed Mughal

  Project Director