PROJECTS PROPOSED FOR USAID ASSISTANCE
ONGOING PROJECTS |
|
|
(US$ in Millions
Rs in Billions) |
|
|
S# |
Name of Project |
Total Cost |
Expenditure upto
June-2010
(Rs) |
PSDP Allocation for 2010-11
(Rs) |
Releases so far
(Rs) |
Request for USAID Funds during 2010-11 |
|
|
A.
Under Implementation (2010-11)
|
|
|
1 |
Gomal Zam Dam (South Waziristan)
Agreement signed on 7.1.2011 |
$ 150
Rs 12.8 |
7.6 |
0.8 |
0.2 |
$ 40.0
Rs 4.0 |
|
|
2 |
Satpara Dam (Gilgit-Baltistan)
Agreements signed on 7.1.2011 |
$ 52
Rs 4.4 |
2.7 |
0.2 |
0.03 |
$ 26.0
Rs 2.3 |
|
|
3 |
Repair and
Maintenance of Units 1, 3 & 4 Of Tarbela Dam
Agreements signed in May 2010 |
$ 320
Rs 27.2 |
|
|
|
$ 16.5
Rs 1.4 |
|
|
|
|
|
TOTAL (A) |
$ 82.5
Rs 7.7 |
|
|
B. Proposed New Projects for USAID (2010-11/2011-12) |
|
|
1 |
Diamer Basha Dam (NWFP.Gilgit Baltistan) |
$ 11178
Rs 950.0 |
3.3 |
15.0 |
2.5 |
$ 50
Rs 17.0 |
|
2 |
Kurram Tangi Dam (North Waziristan) |
$ 700
Rs 59.0 |
0.05 |
0.2 |
- |
$ 2
Rs 0.2 |
|
3 |
Upgradation (E&M)* of Mangla Hydel Power Station (AJK) |
$ 508
Rs 42.5 |
- |
- |
- |
$ 2
Rs 0.2 |
|
4 |
Upgradation (E&M)*of Warsak Hydel Power Station (KPK) |
$ 304
Rs 25.5 |
- |
- |
- |
$ 2
Rs 8.5 |
|
5 |
Training & Capacity Building |
$ 21
Rs 1.8 |
|
|
|
$
Rs |
|
|
|
|
|
|
TOTAL (B) |
$ 56
Rs 4.8 |
|
|
|
|
|
G. TOTAL (A+B) |
$ 692.5
Rs 59.6 |
|
|
* Electro-Mechanical Equipment |
|
|
USAID Assistance requested for ongoing projects Year
2010-11
US$ 82.5 Million
Rs 7.7 Billion
USAID Assistance requested for new projects for the year
2010-11
US$ 56 Million
Rs 4.8 Billion
USAID Assistance requested for ongoing/ new projects
(2011-17)
US$ 3363 Million
Rs 285.9 Billion
|
|