BASHO HYDROPOWER PROJECT |
|
Location |
|
The proposed scheme is identified along 1 km lower
stretch of Basho Lungma, a left tributary of Indus
River. The confluence of Basho Lungma with Indus River
is located about 40 km north-west of Skardu town and 704
km north-east of Islamabad. |
 |
|
Scope
of Work |
|
Detailed
Engineering Design and preparation of Tender Documents. |
|
Objectives/Benefits |
|
To design
a power house of 28 MW Hydropower
to generate mean annual hydroelectricity of 135 GWH. |
|
Date of
Commencement |
|
September
2009 |
|
Date of
Completion |
|
March
2011 |
|
Project
Cost As Per PC-II |
|
PC-II of
the Project approved on 02-09-2002 for Rs. 13546.8
Million with FEC of Rs. 6608.221 Million Million. |
|
SALIENT FEATURES |
|
Design
Capacity MW |
28
|
|
Design
Discharge m3/sec |
3.5 |
|
Gross Head
M |
949 |
|
No. & Type
of units (Pelton) |
3 |
|
Mean
Annual Energy
GWH |
135 |
|
PRESENT STATUS
|
-
Feasibility
report was completed by HEPO (WAPDA) in technical collaboration
with German Agency for technical cooperation GTZ.
-
The updated RFP
duly vetted by AFD/KfW has been sent to central
contract cell (CCC) WAPDA for their approval CCC has
suggested certain modifications which are being
incorporated.
ge
of the Project
Engr. Maqsood Shaffiq Qureshi
General Manager (Hydro) Planning
Wapda Sunny View, Lahore.
Contact No. 9202717
Mobile No. 0333-4691464
|
|
Updated
15.01.2010
|