PROJECT
CONSULTANTS
JV of M/s
Mott MacDonald Ltd (Lead Partner) M/s Sogreah M/s
Nippon Koei Co Ltd M/s MM Pakistan (Pvt) Ltd and M/s DMC.
PRESENT STATUS / PROGRESS
· Pre-feasibility
report of the Project has been prepared in March 2005.
Draft
Feasibility Report was submitted by the Consultants on
March 31, 2009.
· Comprehensive
model studies are in progress at Irrigation Research
Institute (IRI) Nandipur Model studies for sectional
model spillway have been completed. Models for low mid
level and tailrace outlets are being constructed for
testing.
.
For 4 No. Exploratory Adits
in dam Area have been completed. The award of contract
for exploratory Adits in Powerhouse and Surge areas are
at final stage. The evaluation of bids for Exploratory
Adits in MMT/Fault Zone is in progress.
·
Drilling in dam and powerhouse areas at new structure
location is in progress. Upto date 10116 m
drilling has been completed against 10590 m. 536 m River
bed drilling in dam area has been completed by Tarbela
Dam Structure Division WAPDA.
. Suspended
sediment samples at Gainji Bridge, Kachura Alam Bridge
and Bunji Bridge have been collected and analyzed by
ISRIP, WAPDA. Intensive sediment sampling has been
carried out during the year 2009 and is being continued
for year 2010.
Incharge
of the Project
Engr. Maqsood Shafiq Qureshi
General Manager (Hydro) Planning
WAPDA Sunny View Lahore.
Contact No. 99202717
Mobile No. 0333-4691464
|