Hydro Planning
Organization in association with short term
consultants has finalized a Pre-Feasibility report
in March 2005.
-
ECNEC approved the
PC-II for carrying out feasibility study and
detailed design on 14.12.05 for Rs.832.716 million
inclusive of FEC of Rs.232.733 million.
-
Contract Agreement
signed between WAPDA and Joint Venture of Mott
MacDonald Ltd (Lead Partner), Sogreah Consultants
SAS, Nippon Koei Co; Ltd, MM Pakistan (Pvt) Ltd, DMC
Consultants for Feasibility Study, Detailed
Engineering Design and preparation of Tender
Documents.
-
The inception
Report comprising of 2 Volumes was submitted by
Consultants on August 09 2007. The comments on
inception report were communicated to consultants
for incorporation.
-
Reviews of
different alternative about dam and powerhouse sites
are under study by the Consultants for final
selection of layout.
-
Survey and field
investigations through core drilling, geological
mapping, hydrographic survery and geophysical survey
are in progress.
-
The establishment
of field office of WAPDA at Gilgit is in progress.
-
A presentation by
Bunji Hydropower Consultants was given to Chairman,
WAPDA on 16 June 2008.
-
The Study will be
completed in April 2010.
-
The Study will be
completed in April, 2010.