CONSTRUCTION OF 444 DRAINAGE TUBEWELL IN MIRPUR KHAS (UNDER NDP)
Location Mirpurkhas & Sanghar District of Sindh.
Project Incharge Mr. Mr. Shafqat Ali Samejo
Phone Direct: (0221) 9260028 Fax: (0221) 9260027
BPX: (0221) 92401158-8 / 265
Time Lines
Initial Date Schedule completion date Allocated budge
03.08.2001
Start of 1st. contract of drilling
T20.ND1A

30.06.2004

420.390 Million (FY 2001-2002)
331.480 Million (FY 2002-2003)
419.002 Million (FY 2003-2004)
125.622 Million (FY 2004-2005)
148.000 Million (FY 2005-2006)
119.000 Million (FY 2006-2007)
210.000 Million (FY 2007-2008)
Approvals
Approving Authority
Govt. of Pakistan (Ministry of Water & Power)
PC-2   Cost
-   -
PC-1   Cost
    677.00 Million
ECNEC   Cost
    677.00 Million
Funding Agency
(i) Asian Development Bank (ADB) 
(ii) Government of Pakistan (GOP)
Performance report as on 31.05.2008
Behind .........days On Target Ahead ........days
Present Status
Construction of Drainage Tubewells-II in Mirpurkhas Sub Project Area (240 Tubewells) Contract Nr. T20.ND1A 100%
Construction of Drainage Tubewells-II in Mirpurkhas Sub Project Area (240 Tubewells) Contract Nr. T20.ND1B 100%
Supply, Delivery & Installation of Pumping Equipment for Drainage Tubewells in Mirpurkhas, Nawabshah & Sanghar Sub Project Areas Contract Nr.T25.ND3 100%
Construction & Completion of Disposal Channels for Drainage Tubewells II&III in Mirpurkhas & Sanghar Sub Project Areas Contract Nr.T15.ND2 98.25%
Key mile stone Plan Actual / Expected
Construction for Drainage Tubewells-II in Mirpurkhas Sub Project Area (240 tubewells) Contract Nr.T20.ND1A 24.01.2003 24.01.2003
Construction for Drainage Tubewells-II in Mirpurkhas Sub Project Area (204 tubewells) Contract Nr.T20.ND1B 24.01.2003 31.01.2005
Supply, Delivery & Installation of Pumping Equipment for Drainage Tubewells in Mirpurkhas, Nawabshah & Sanghar Sub Project Areas Contract Nr.T25.ND3 15.11.2003 23.09.2005
Construction & completion of Disposal Channels for Drainage Tubewells in Mirpurkhas & Sanghar Sub-Project  Areas Contract Nr.T15.ND2 07.10.2004 31.03.2006
(Major works completed )
Key Issues    
Description

Reference

Resolved by

- - -
Financial Status 2007-2008 (P)
  a b c d e f
Initial Budget Current Budget Actual Spend  date R/Cost to completed Var. Reason
Fixed            
Admn + Central Payment   0  

-

   
Over Heads & Interest -    

-

   
Variable            
Consultants -    

-

   
Assets -    

-

   
Works 210.000 210.000 1.800

-

   

Total

210.000

210.000

       

Note Variation = (c + d) - b

Other Comments
NIL