|
DASU HYDROPOWER PROJECT |
|
Location |
|
Dasu hydropower project
is a run of river scheme located 7 km upstream of Dasu
village on Indus River, 74 km downstream of Diamer Basha
Dam and 350 km from Islamabad. The Project is located in
district Kohistan of Khyber Pakhtunkhwa. |
 |
| Scope
of Work |
|
Preparation of
Detailed Engineering
Design Tender Documents and Project Construction. |
| Objectives/Benefits |
| To
Design a Project of 4320 MW to produce mean annual
hydroelectricity of 21300 GWh. |
| Date
of Commencement |
|
April
2010 |
| Date
of Completion |
|
March 2019 |
| Project
Cost As Per PC-II |
PC-II
was approved by ECNEC on 29.09.2003 at a total cost of Rs.
796.87 Million, with FEC Rs. 100.00 million.
- Stage-I (Feasibility study) for Rs.540.902 million with FEC Rs. 60.00 Million.
- Stage-II (Detailed Engineering Design and Tender
Documents) for Rs.255.876 Million with FEC Rs. 40.00
Million |
|
SALIENT FEATURES |
|
Installed
Capacity MW |
4320 |
|
Mean Annual
Energy GWH |
21300 |
|
Design
Discharge m3/Sec |
2600 |
|
Type of
Dam |
RCC |
|
Gross Head
(M) |
233 |
|
Construction
Period (Years)
|
8 |
|
No. & Type
of Turbine |
8 |
|
Project
Base Cost |
US$ 5.28
Billion |
|
PROJECT CONSULTANTS |
|
The
Feasibility study of the Project completed on 28th
February, 2009 by a Joint
Ventureof M/s NESPAK (Lead Firm) , ACE, MWH and COLENCO
in association with Binnie & Partners UK. |
|
KEY PROGRESS |
|
-
06 Nos. Micro-Seismic Stations have been
established in the project area.
- River bed drilling,
one bore hole about 51 meter deep had been completed at
U/S Coffer Dam Site during the
March, 2011.
- Steering Committee
of WCAP has approved US$ 8.0 million on October, 2011
for detailed Engineering Design
and Tender
Documents & Tendering of Dasu HPP.
-
The Consultancy Contract Agreement for preparation and
Implementation of Dasu Hydropower Project has been
signed on September 19, 2011 between Dasu Hydropower
Consultant and WAPDA.
- Dasu
Hydropower Consultant (DHC) was mobilized and commenced
their services from September 19, 2011.
- Kick of
meeting with Dasu Hydropower Consultant (DHC)
was held on September 24, 2011 in the office of Project
Director Dasu HPP.
- Mr. Masood Ahmad,
Task Leader, World Bank along with Mr. Muhammad Saqib,
Sr. Energy specialist and Mr.
Anjum Ahmad,
Sr. Energy & PPP Specialist visited DHC office, Lahore
and hold meeting with and Mr. Anjum
Ahmad, Sr.
Energy & PPP Specialist visited DHC office , Lahore and
hold meeting with DHC and Project Director,
Dasu HPP and
his team. During meeting Project scheme was discussed in
detail.
- DHC has
submitted invoices for Advance of Pakistan Rupee
portion, Euro Portion and Japanese Yen Portion along
with the Bank
Guarantees. After approval from General Manager (Hydro)
Planning, the invoices have been
forwarded to
General Manager (C&M) Water, WAPDA for further
processing.
- PD (Dasu) Field
Office has been established at Dasu Town District
kohistan since November 2011.
- Inception Report of
Dasu Hydropower Project was received from DHC on
November 29, 2011. |
|
Progress During the Month |
-
River bed drilling at Main Dam Axis -5 has been re
started from December
11,2011
about 26 meter deep bore
hole has been completed so far during the month.
- DHC hired the services of Dr. Muhammad Zaman,
International Resettlement & Social Expert
to Strengthen the
Social Team.
- Project Director, Dasu had meeting with Environmental
& Social Team of DHC on December 02, 2011 in the
office
of DHC, Lahore. Environment & Social Development Plan were discussed in
detail.
- Mr. James Ramasy, International Environment Expert
Joined DHC Office, Lahore on December 02, 2011.
- Project Director, Dasu had meeting with Environmental
Team of DHC on December 08, 2011 in the office of DHC,
Lahore. Terms of Reference (TOR). Table of contents (TOC) and Methodology
to carry out the environmental
studies were discussed in detail.
- Mr. James Ramsey, International Environment Expert
along with Environmental Team of DHC and XEN, Dasu HPP,
WAPDA v isited the Dasu Project site from December 11, 2011 to December
15, 2011 and had meeting
with the District Coordination Officer (DCO), District Poilice Officer (DPO)
and other concerned local Government
Officials of District Kohistan, Khyber Pakhtunkhwa to discuss the
establishment of consultation mechanism in
Dasu Project Area.
- Project Director, Dasu had meeting with General
Manager (Power) Planning on December 12, 2011 in his
office.
During the meeting detail about the scope and status of the transmission
line for Dasu HPP were discussed.
General Manager (Power) Planning informed that from Dasu HPP to load
center, 4 circuits of 500 KV transmission
line on 2 Double Circuit towers have been finalized by the Consultants
for the power evacuation of Dasu
HPP. He also explained that scope of Design, Construction and Financing
of the transmission line is the
responsibility of NTDC.
- Project Director, Dasu had meeting with Archeology &
Fisheries Specialists of DHC on December 13, 2011 in the
office of Project Director, Dasu. TOR and TOC for Cultural Resources and
Fisheries were discussed in detial &
finalized.
- Project Director Dasu had meeting with infrastructure
Team of DHC on Cecember 15, 2011 in the office of
Project
Director, Dasu. Different site locations for O&M Staff Colony, WAPDA &
Consultant Colonies during construction,
offices, Resettlement Colony and Civic Facilities were discussed in
detail.
- Project Director, Dasu office received 2nd invoice
from DHC on December 15, 2011. Scrutiny and verification
of
invoice is in process.
- Project Director, Dasu had meeting on December 17,
2011 with Project Manager, DHC, Deputy Project Manager,
DHC and Mr. James Ramsey, International Environment Expert in the office
of DHC, Lahore. During the meeting
Mr. James Ramsey explained about the consultation strategy in the light
of meetings held with local Government
officials during the visit.
- Project Director, Dasu along with Project Manager, DHC
and his team visited Irrigation Research Institute,
Hydraulic
Model Study Cell, Nandipur on December 20, 2011.
- Project Manager, DHC along with his team delivered
presentation on Inception Report of Dasu HPP on December
21, 2011 in the Committee Room of WAPDA House, Lahore. Worthy
Member (Water), General Manager (C&M),
General Manager (Hydro) Planning, General Manager (CCC), General Manager
(CDO), General Manager (Power)
Planning, Abdul Khaliq Khan (Consultant to WAPDA on Mega Projects), Dr.
Izharul Haq, Mr. Muhammad Siddique
(Advisor) and other High Officials of WAPDA attended the
Presentation.
|
Incharge
of the Project
Haji M. Farooq Ahmad
Project Director
Wapda Sunny view Lahore.
Contact No. 0092-42-99202676
Mobile No. 0300-43055956 |
|
Updated
31.12.2011
|
|
|