|
GOLEN GOL HYDROPOWER PROJECT |
|
Location |
|
The
project is located on Golen Gol Nullah, a tributary of
Mastuj River, 25 Km from Chitral Town in KPK.
|
 |
|
SCOPE OF WORK |
|
Construction of O&M Staff Colony LOT-1 Civil Work Lot-2
Civil Works of power House Lot-3.1 E&M Works Lot-3.2
and Transmission Line Lot-4 |
|
OBJECTIVES / BENEFITS |
|
To
Generate 106 MW Hydel Electricity |
|
DATE OF COMMENCEMENT |
|
As Per
PC-I |
Revised |
|
July 2002 |
July 2010 |
|
DATE OF COMPLETION |
|
As Per
PC-I |
Revised |
|
June 2006 |
July 2014 |
|
PROJECT COST AS PER PC-I / PC-II |
Rs.
7035.128 Million |
|
SALIENT FEATURES |
|
Installed
Capacity MW |
106
|
|
Annual
Energy GWH |
436 |
|
Design
Discharge |
30 m3/sec |
|
Tunnel
Length |
3.8 KM |
|
Design
Head |
435 M |
|
PRESENT STATUS / PROGRESS |
-
LOT-1 COLONY
Date of commencement February 2009
Date of completion February 2011
Contract for O&M Staff Colony Koghuzi Chitral has
been awarded to Contractors. Work at site is in
progress & achieved 54% while target progress upto
June 2010 is 50%.
-
LOT-2 & 3.1 Civil Works /Power House
Contracts for Civil work Lot-2 and Lot-3.1
have been opened on 15.04.2010 and approved by the
Authority. The concurrence of the Donors is awaited.
LOT 3.2 E&M Works Pre-qualification of contractors has been
finalized and tenders will be floated shortly.
-
LOT-4 Transmission Line
Pre-qualification documents of firms
have been vetted by the donor and tenders will
be floated shortly.
-
Expression of Interest (EOI) re-advertised for
hiring of consultants has been received on 20th
March 2010 and approved by competent authority. RFPs
have been issued to short listed firms / JVs on
07.05.2010 and submission date is 30.06.2010 and
financial progress overall 6.89.
Incharge
of the Project
Mr.Ishtiaq
Anwar
Project Director
Golen Gol Hydropower Project WAPDA Chitral
Phone No.0943-413473 Chitral
091-9212041-47 Ext. 325 Peshawar |
|
Updated as on
30.06.2010 |