GOLEN GOL HYDROPOWER PROJECT

Location

The project is located on Golen Gol Nullah, a tributary of Mastuj River, 25 Km from Chitral Town in Khyber Pakhtunkhwa.

SCOPE OF WORK
Construction of O&M Staff Colony LOT-1 Civil Work Lot-2 Civil Works of power House Lot-3.1 E&M Works Lot-3.2 and Transmission Line Lot-4
OBJECTIVES / BENEFITS
To Generate 106 MW Hydel Electricity
DATE OF COMMENCEMENT

As Per PC-I

Revised

July 2002

February 2011

DATE OF COMPLETION
As Per PC-I Expected
June 2006 February 2015
PROJECT COST AS PER PC-I / PC-II Rs. 7035.128 Million
SALIENT FEATURES
Installed Capacity MW 106
Annual Energy GWH 436
Design Discharge 30 m3/sec
Tunnel Length 3.8 KM
Design Head 435 M
PRESENT STATUS / PROGRESS
  • LOT-1 COLONY

    Date of commencement February 2009
    Date of completion February 2011

    Construction of O&M Staff Colony Koghuzi is in progress & achieved 82% upto June 2011 and will be completed in 2011.

    LOT-2 & 3.1 Civil Works /Power House
    Date of commencement for the Contract Lot 2 & 3.1 (Civil Works) was 01.02.2011. Contractor M/S Sambu has been mobilized to site and preparatory works are in progress.

    LOT 3.2 E&M Works
    Tenders for Lot-3.2 (E&M Works) opened on 30.06.2011 and sent to Consultants for evaluation.

  • LOT-4 Transmission Line
    After authority has decided to invite bids on post qualification basis, the amended bidding documents (post qualification basis) have been sent to the donors for seeking concurrence.

  • Consultancy agreement for construction supervision has been signed, the consultant will mobilized at site shortly.

Incharge of the Project

Mr. Ishtiaq Anwar
Project Director
Golen Gol Hydropower Project WAPDA Chitral
Phone No.0943-413473 Chitral
091-9212041-47 Ext. 325 Peshawar

Updated as on 31.10.2011