|
GOLEN GOL HYDROPOWER PROJECT |
|
Location |
|
The
project is located on Golen Gol Nullah, a tributary of
Mastuj River, 25 Km from Chitral Town in Khyber
Pakhtunkhwa.
|
 |
|
SCOPE OF WORK |
|
Construction of O&M Staff Colony LOT-1 Civil Work Lot-2
Civil Works of power House Lot-3.1 E&M Works Lot-3.2
and Transmission Line Lot-4 |
|
OBJECTIVES / BENEFITS |
|
To
Generate 106 MW Hydel Electricity |
|
DATE OF COMMENCEMENT |
|
As Per
PC-I |
Revised |
|
July 2002 |
February 2011 |
|
DATE OF COMPLETION |
|
As Per
PC-I |
Expected |
|
June 2006 |
February
2015 |
|
PROJECT COST AS PER PC-I / PC-II |
Rs.
7035.128 Million |
|
SALIENT FEATURES |
|
Installed
Capacity MW |
106
|
|
Annual
Energy GWH |
436 |
|
Design
Discharge |
30 m3/sec |
|
Tunnel
Length |
3.8 KM |
|
Design
Head |
435 M |
|
PRESENT STATUS / PROGRESS |
-
LOT-1 COLONY
Date of commencement February 2009
Date of completion February 2011
Construction of O&M Staff Colony Koghuzi
is in progress & achieved 82% upto June 2011
and will be completed in 2011.
LOT-2 & 3.1 Civil Works /Power House
Date of commencement for the Contract Lot 2 & 3.1
(Civil Works) was 01.02.2011. Contractor M/S Sambu
has been mobilized to site and preparatory works are
in progress.
LOT 3.2 E&M Works Tenders for
Lot-3.2 (E&M Works) opened on 30.06.2011 and sent to
Consultants for evaluation.
-
LOT-4 Transmission Line
After authority has decided to invite bids
on post qualification basis, the amended bidding
documents (post qualification basis) have been sent
to the donors for seeking concurrence.
-
Consultancy agreement for construction supervision
has been signed, the consultant will mobilized at
site shortly.
Incharge
of the Project
Mr. Ishtiaq
Anwar
Project Director
Golen Gol Hydropower Project WAPDA Chitral
Phone No.0943-413473 Chitral
091-9212041-47 Ext. 325 Peshawar |
|
Updated as on
31.10.2011 |