GOLEN GOL HYDROPOWER PROJECT

Location

The project is located on Golen Gol Nullah, a tributary of Mastuj River, 25 Km from Chitral Town in KPK.

SCOPE OF WORK
Construction of O&M Staff Colony LOT-1 Civil Work Lot-2 Civil Works of power House Lot-3.1 E&M Works Lot-3.2 and Transmission Line Lot-4
OBJECTIVES / BENEFITS
To Generate 106 MW Hydel Electricity
DATE OF COMMENCEMENT

As Per PC-I

Revised

July 2002

July 2010

DATE OF COMPLETION
As Per PC-I Revised
June 2006 July 2014
PROJECT COST AS PER PC-I / PC-II Rs. 7035.128 Million
SALIENT FEATURES
Installed Capacity MW 106
Annual Energy GWH 436
Design Discharge 30 m3/sec
Tunnel Length 3.8 KM
Design Head 435 M
PRESENT STATUS / PROGRESS
  • LOT-1 COLONY

    Date of commencement February 2009
    Date of completion February 2011

    Contract for O&M Staff Colony Koghuzi Chitral has been awarded to Contractors. Work at site is in progress & achieved 54% while target progress upto June 2010 is 50%.

  • LOT-2 & 3.1 Civil Works /Power House
    Contracts for Civil work Lot-2 and Lot-3.1 have been opened on 15.04.2010 and approved by the Authority. The concurrence of the Donors is awaited.

    LOT 3.2 E&M Works
    Pre-qualification of contractors has been finalized and tenders will be floated shortly.

  • LOT-4 Transmission Line
    Pre-qualification documents of firms have been vetted by the donor and tenders will be floated shortly.

  • Expression of Interest (EOI) re-advertised for hiring of consultants has been received on 20th March 2010 and approved by competent authority. RFPs have been issued to short listed firms / JVs on 07.05.2010 and submission date is 30.06.2010 and financial progress overall 6.89.
     

Incharge of the Project

Mr.Ishtiaq Anwar
Project Director
Golen Gol Hydropower Project WAPDA Chitral
Phone No.0943-413473 Chitral
091-9212041-47 Ext. 325 Peshawar

Updated as on 30.06.2010