GOMAL ZAM DAM PROJECT (GZDP)
Scope of Work

Construction of Roller Compacted Concrete Dam 437 ft. High, Reservoir having a gross storage of 1.14 MAF, Command Area 1,63,086 Acres with Power House of 17.4 MW Capacity, Barrage at Kot Murtaza, Length of Main Canal 60 KM.

TIME LINES
  Planned Expected
PC-I June - 2007 October - 2010
APPROVAL    
  Rs. In Million Remarks
 

12829

CDWP ECNEC
    June - 2001 August - 2001
PERFORMANCE REPORTS AS ON 30.11.2008
  Behind ...... days On target Ahead ..... days
GZD-01 EPC/Turnkey
Present Status
Contract with M/S CWHEC-HPE-JV (Chinese Firm) terminated w.e.f. 14.04.2006
GZD-02 EPC/Turnkey
Work re-started on site on 11.06.2007
FINANCIAL STATUS 
 (Rs. In Million)
Head of Account

Expenditure upto 30.06.2008  (F)

Budget Allocation 2008-09

Expenditure in FY 2008-09 upto 30.11.2008

Total Expenditure upto 30.11.2008

Admn 293.98 70.000 30.257 324.237
Overhead  76.789 45.000 18.750 95.539
Consultants 101.726 60.000 8.384 110.110
Assets 4.654 1.000 - 5.008
Works/Land Cost 2463.81 1824.000 505.094 2968.904
Total: 2940.959 2000.000 562.485 3503.798

Advance / Deposits

    138.212  
TOTAL

2940.959

2000.00

424.273 3365.232

GOMAL ZAM DAM PROJECT