The
Proposed scheme is identified along 2.5 km lower stretch
of Harpo Lungma, a left tributary of Indus River in
Rondu Area, district Skardu. The project area is located
75 km north-west of Skardu town and 670 km north-east of
Islamabad.
SALIENT FEATURES
Insatallated Capacity MW
33
Gross Head
M
716
Design
Discharge m3/Sec
5.5
Channel
Length M
410
Penstock
Length M
2885
No. of
Units
3 Pelton
Energy
Generated
GWh
187
Tentative
Project Cost
Million
US$
40
PRESENT STATUS
Feasibility study
of the project completed with the technical
collaboration of GTZ of Germany.
PC-II for Detail
Design and preparation of Tender Documents has been
prepared and ready for submission to GoP for
approval.