JINNAH HYDROPOWER PROJECT
|
|
Location
The Project is located on the right side of existing
Jinnah Barrage, 5 km from Kalabagh town in District
Mianwali and 234 km from Islamabad. |
 |
|
Scope
of Work |
|
Construction
of 96 MW Hydropower Project |
|
Objectives/Benefits |
|
To produce
mean annual hydroelectricity of 688 GWH. |
|
Date of
Commencement |
|
Project
Commencement
date 18th February 2006 |
|
Date of
Completion |
|
First unit
is expected to be commissioned in December, 2011 and all
the 8 units will be completed upto December 2012. |
|
Project
Cost As Per PC-I |
|
PC-I of
the Project approved on 02-09-2002 for Rs. 13546.8
Million with FEC of Rs. 6608.221 Million. |
|
SALIENT FEATURES |
|
Installed
Capacity
(MW)
|
96 |
|
Gross Head
(m) |
4.88 |
|
Mean Annual
Energy (GWh) |
688 |
|
Design
Discharge (m3 /sec) |
2400 |
|
No.
& Type of Turbine |
8-Pit Type
|
|
Turn Key
Cost (Million US$) |
128 |
|
Implementation Period
(Years) |
4 |
|
PROJECT CONTRACTOR |
|
M/s Dongfang Electric Corporation (DEC) of China. |
|
PROJECT CONSULTANTS |
|
JV of M/s
ACE (Pvt) Ltd. (Lead Partner), M/s NESPAK, M/S NDC, M/s
MWH in association with M/s NESEPAK and M/s DMC. |
|
PRESENT STATUS /PROGRESS |
Physical Progress *87.73%
* The Physical Progress of the Project before the
flooding event of July 2010 was 95.5%. Due to the adverse effects of
the flood, it had been reduced to 77.5%.
|
JINNAH
HPP
The Status of works at Project site is as under.
- Tentative civil works Progress is 99.12%.
- All works in Headrace/Tailrace Channels
are completed and the erection works of unit #1 are
almost
completed except the generator. It is reported that the
commissioning of Unit #1 will be started at the end
of November, 2011. |
|
O&M
Staff Colony |
|
- PC-I for the
construction of O&M staff colony was approved on
19-11-2009 for Rs. 253.07 million.
|
Latest Status
- A Team of CDO (Water) WAPDA visited the site on 27th
July 2011 and advised the project authorities to carry
out certain field tests at the proposed location in
order to evaluate the critical design parameters. On the
basis of these results the confirmation of the location
and relative changes in the design of O&M staff colony
will be carried out.
- CMTL has been asked to visit the proposed site for
colony to take the samples for the test as recommended
by CDO, WAPDA.
- CMTL has submitted the initial analysis report. The
teazm of CMTL will again visit the project site for
making more bore holes at the proposed location after
which final analysis report will be submitted by CMTL. |
|
Incharge
of the Project
Engr. Amir
Baksh Mirani, Chief Engineer & Project Director
Jinnah Hydropower Project
Kalabagh Town, District Mianwali
Contact No. 0459-399303
Mobile No. 0300-8005175 |
|
Updated
31-10-2011 |
 |