|
KACHHI CANAL PROJECT | ||||||
| Location |
Districts: Muzaffargarh, D.G. Khan &
Rajanpur of Punjab | |||||
| Scope of Work |
Construction of Head Regulator at Taunsa Barrage on Indus River Main Canal about 500 km (300 km lined canal in Punjab and 200 km unlined canal in Balochistan) Distribution system 1500 km. | |||||
| Objectives/Benefits |
The main objective of the project is to provide sustainable irrigation water supply to 7,13,000 acres of agricultural land so as to increase agricultural production and uplift the socio economic condition of the inhabitants. | |||||
| Date of Commencement | October 04.2002 | |||||
| Date of Completion | June 30, 2007 (as per PC-I) Dec 31, 2013 (Phase-I) Revised Dec 31, 2014 (Phase-II) June 30, 2015 (Phase-III) |
|||||
| Project Cost (As per PC-I) | Rs.31204 Million approved by ECNEC on 27.09.2003 | |||||
| Salient Features | 1. Main Canal a. Canal in Punjab b. Canal in Balochistan Distribution System Structure a. Major b. Minor EIRR |
300 km lined 200 km Unlined 1500 km |
||||
| Present Status / Progress |
Land (Acres) |
E/Work Mcft. |
Lining Mcft |
Structures | ||
| Project components |
32492 |
6895.848 | 56.506 | Major 235 Minor 2236 | ||
| Physical Achievement upto August 2011 |
18535 |
3207.767 | 35.674 | 207 No. structures 100% completed. Concrete: 8.487 Mcft Piles:272041 Rft. | ||
| Scope of work 2011-12 |
- |
39.00 | 1.20 | 8 Nos.minor | ||
| Physical Achievement during 2011-2012 |
- |
- | 0.019 | Concrete 33.67 cft. | ||
| Contact No. |
Maulla Bux Jamro Chief Engineer / PD 248 - C Khayaban-e-Sarwar D.G.Khan 064-2468498, 0649260636 Fax No. 064-2468398 | |||||
| Updated upto 30.11.2011 | ||||||
| LOCATION MAP | Attached | |||||