· Feasibility
Report completed in October, 2007.
. Loan Project Agreement Euro 79 Million between GOPand Kfw of Germany signed on November 11 2008
for implementation of the Project. Supplementary
loan Agreement Euro 20 Million signed on
11.04.2009.
.
The Authority in its meeting held on 31-03-2010
accorded approval for engagement of Consultants
JV comprising M/s Lahmeyer Germany as lead Firm
in association with M/s NDC and EASE PAK at a
cost of Rs. 525,207.502.50 and Euro
6,611,591,50.
. Contract agreement for consultancy services
signed with Keyal Hydropower consultants (KHPC)
on May 12, 2010 in prsence of Federal Minister
for Water and Power and Chairman WAPDA for
prepartion of detailed Engineering Design &
Tender Documents and Construction supervision.
. M/s Lahmeyer International (JV)
has started their consultancy services w.e.f
01.06.2010.
. Relending of loan has been taken up with
Government of Pakistan Loan term decided by ECC
in its meeting held on June 30, 2011.
.
Final detail Engineering Design report received
from Consultant during 2nd week of December
2011.
. Guage observations have been started at Peshawa
and Shenshal after installing new gauges. Gauge
observations are being carried out by Surface
Water Hydrology, WAPDA.
.
The report on Bathymetric survey of Indus River
to update the tail water curve is completed by
ISRIP, WAPDA.
.
Drilling at bore hole is in progress by DID,
Wapda. Upto date 1288.5 m drilling has been
completed against 1415.0 M.
. An other Contractor image Tech Universal
Engineering JV is hired for geotechnical
investigation of bore hole No. Sh-03. Drilling
started on 22.08.2011 and upto date 203 m
drilling has been completed against 350 m.
.
The Authority in its meeting held on 27.09.2011
accorded approval for award of contract for
ventilation tunnel to M/s Sarwar & Co (Pvt) Ltd
at a cost of Rs. 109.322 Million. The letter of
acceptance and performance Security has been
received from Contractor. Consent from KFW for
signing of Contract Agreement is awaited.
.
CDO, WAPDA has been involved for Planning &
Designing of Office & Staff Colony. The
following designs are awaited from CDO.
- Architectural design of Rest houses and Staff
Hostel.
- Structural & foundtion design of school, Rest
house and staff
hostel
.
The letter of acceptance for construction of O&M
Staff Colony at Pattan Lot-1 (Consturction of
Colony Infrastructure Internal Roads, Water
Supply and Sewerage System) has been issued to
lowest Bidder M/s Muhammad Naeem & Co.
Contract Agreement is prepared for signing. Further four lots amounting to Rs. 4.0
million for Staff Colony was advertised and
opened on 19.11.2011.
.
After analysis tender has been canceled as the
rate quoted by Contractors are higher. Further
three more lots were advertised. Tenders opened
on 27.12.2011 are in process of Award.
.
Excavation of Power from Keyal HPP and its
interconnection to under constructed Dubair HPP
switchyard was discussed with High Head
Consultants and Director Technical General
Manager (Northern Area). It was concluded that
one additional bay at Dubair switchyard may be
construction by Contractor working at present.
Estimate was received and forwarded to Kfw for
consent.
.
The hydraulic model study has been completed by
IRI Nandipur.
Report is awaited.
-
Incharge
of the Project
Engr.
Hasnain Afzal
General Manager (Hydro) Planning
Wapda Sunny View, Lahore.
Contact No.0092-42-99202717
Mobile No. 0092-0300-4691464