· KfW
of Germany is financing under grant for preparation
of feasibility study of he project. M/s ILF of
Germany JVs has been appointed as consultants for
the project studies. Consultancy
Contract Agreement was signed on 29.07.2006 and
Consultants mobilized in August 2006.
· The
Consultants finalized the Phase-I study Ranking and
Pre-feasibility study of hydropower projects in
February 29, 2008.
· As
per Phase-I, study Lower Palas Schemes 621 MW is
ranked first to be taken up for feasibility study.
The other identified projects are middle Palas 398
MW and upper Palas 157 MW.
· The
Consultants have completed Phase-II. Feasibility
study of Lower Palas Schemes 665 MW.
The Feasibility Report
has been finalized in June 2010.