· KfW
of Germany is financing under grant for preparation
of feasibility study of the project. M/s ILF of
Germany JVs have been appointed as consultants for
the project studies. Consultancy Contract Agreement
was signed on 29.07.2006 and Consultants were mobilized
in August 2006.
.
Consultancy Contract Agreement was signed on
29-07-2006 and Consultants mobilized in August 2006.
.
As per Phase-I Study, Lower Spat Gah Scheme (567 MW)
is ranked first and taken up for feasibility study.
The other identified projects are Middle Gabarband
(489 MW) and upper Spat Gah (252 MW).
.
As per Phase-II, after having site investigations
and data collection, the Consultants submitted Draft
Feasibility Report of 496 MW Lower Spat Gah Scheme
in November 2009.
.
After incorporating comments of WAPDA, KfW and POE,
the Consultants have submitted the Feasibility
Report in June 2010.
.
WAPDA Authority in its meeting on 31-08-2010 has
decided to implement Lower Spat Gah Scheme in Public
Private Partrnerhsip (PPP) Mode. EOI documents for
PPP mode have been prepared in Consultation with CCC,
WAPDA and IPDF, Islamabad.
.
EOI Notice has been published in the local newspaper
on 12-07-2011. EOI documents are being issued tyo
interested sponsors. The last date for submission of
EOI initially fixed as on 01.10.2011, has extended to 18.11.2011. Three bids
are submitted and the evaluation of bids is in progress.
Incharge
of the Project
Engr. Hasnain Afzal
General Manager (Hydro) Planning
Wapda Sunny View, Lahore.
Contact No. 0092-42-99202717
Mobile No. 0092-0300-8411244 |